Severn Power REMIT

Unit 20 Offline Compressor Wash


Category: Uncategorised




























































Reference number / Reference number 2014/09/25[CJH]-01
Type of asset or agreement Power Plant
Affected unit(s) Severn 20
Country UK
Time of capacity reduction 25.09.2014    -   01.00 hrs
Company Macquarie
Cause Outage
Type of fuel(s) Gas
Capacity influenced 410 MW
Available capacity during outage or maintenance 0 MW
Estimated outage or maintenance duration 25/09/2014   06:00hrs
Duration uncertainty +/- 1 hour
Additional information Unit unavailable for Compressor wash
Event status


From: 25/Sep/2014 01:00

To: 25/Sep/2014 06:00