Baglan Bay REMIT

Steam Valve Issue


Category: Uncategorised

Publication according to Article 4(1) of REMIT - Urgent Market Message - [BMU: BAGE-1]

Posted 26th October 2015 @ 13:20

BMU: BAGE-1 availability increased from 0MW to 460MW from 13:20 26th October 2015.

Steam valve issues resolved

Previous update 26th October 2015 @ 11:10

--------------------------------------------------------------------------------------------------------------------------------------------

 

Posted 26th October 2015 @11:10

BMU: BAGE-1 availability reduced from 460MW to 0MW, between 01:47 26th October 2015 and 14:00 26th October due to steam valve issue.

Previous update 26th October 2015 @ 02:05

 

 

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------

 

(BMU:BAGE1) Availability is reduced from 460Mw to 0 Mw

Steam Valve Issue - Unit 1 Breaker opened during start-up suspect steam valve issue - Investigation on-going

Posted 02:05 hrs 26th October 2015

BMU:BAGE-1 availability is reduced from 460MW to 0MW from 01:47 October 26th 2015 due to steam valve issue. Investigations are on-going.

Current expected return to full availability 12:00 26th October 2015

There were no previous updates

From: 26/Oct/2015 01:47

To: 26/Oct/2015 13:20