Severn Power REMIT

Severn Unit 20 Hot Gas Path Inspection 2020


Category: Maintenance Outage

PUBLICATION ACCORDING TO ARTICLE 4 (1) OF REMIT - ACTIVE MARKET MESSAGE - SVRP 20

Published 09:10 11th January 2016

Unit 20 availability is expected to be 0MW between 23:00 31st of August 2020 and 23:00 6th of October 2020 due to a scheduled Hot Gas Path Inspection

 

From: 31/Aug/2020 23:00

To: 06/Oct/2020 23:00