Severn Power REMIT

Severn Unit-10 unavailable between re-commissioning days


Category: Steam Turbine

Publication according to Article 4(1) of REMIT - URGENT MARKET MESSAGE - SVRP-10

Posted 28/10/2015 @ 14:15

Following on from the previous post, T_SVRP-10 availability is estimated to be 0 MW between 23:30 26 October 2015 and 03:00 29 October 2015, at which point Day 2 commissioning will commence.

This notification replaces the previous post of 27/10/2015 @ 14:15

---------------------------------------------------------------------

Posted 27/10/2015 @ 14:15

Following on from the previous post, T_SVRP-10 availability is estimated to be 0 MW between 23:30 26 October 2015 and 08:30 29 October 2015 in order to carry out a repair on the main steam pipe work.

This notification replaces the previous post of 27/10/2015 @ 00:10

-----------------------------------------------------------------------

Posted 27/10/2015 @ 00:10

Following on from the previous post, T_SVRP-10 availability is estimated to be 0 MW between 23:30 26 October 2015 and 07:00 28 October 2015 in order to carry out a repair on the main steam pipe work.

This notification replaces the previous post of 26/10/2015 @ 23:30

-----------------------------------------------------------------------

Posted 26 October 2015 @ 23:30

This supersedes earlier post dated 25th October 2015 @ 21:30

SVRP-10 availability is reduced from 400MW to 0MW from 23:30 26 October 2015 and 07:00 27 October 2015.  This is the period between re-commissioning days where the unit is completely unavailable.

--------------------------------------------------------------------------------------------------------------------------------------------------------------

Posted 25 October 2015 @ 21:30

This supersedes earlier post dated 23rd October 2015 @ 20:42

SVRP-10 availability is reduced from 400MW to 0MW from 00:00 27 October 2015 and 07:00 27 October 2015.  This is the period between re-commissioning days where the unit is completely unavailable. This is due to delay in the commissioning programme, along with a significant deviation of the plan.

-----------------------------------------------------------------------------------------------------------------------------------------------------------------

Posted 23rd October 2015 @ 20:42

This supersedes earlier post dated 23rd October 2015 @ 15:35

SVRP-10 availability is reduced from 400MW to 0MW from 00:00 27 October 2015 and 06:00 27 October 2015.  This is the period between re-commissioning days where the unit is completely unavailable. This is due to delay in commissioning programme of 24 hours.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------

Posted: 23 October 2015 @ 15:35

SVRP-10 availability is reduced from 400MW to 0MW from 00:00 26 October 2015 and 06:00 26 October.  This is the period between re-commissioning days where the unit is completely unavailable.

There were no previous updates

From: 26/Oct/2015 23:30

To: 29/Oct/2015 03:00