Post-Outage Recommissioning – Day 3


Category: Uncategorised

Publication according to Article 4(1) of REMIT - URGENT MARKET MESSAGE - SVRP-10

Posted: 29 October 2015 @ 20:20

Due to a further revision of the recommissioning plan, there is a new requirement for Day 3 comissioning.

Please see the Day 3 post-outage recommissioning planned profile below (please scroll to the bottom of the post).  Availability is reduced from 425MW to the planned profile.

It must be noted that the planned profile will not change throughout the day of testing, but will be subject to variability.  However, significant deviations to the Day 3 recommissioning, which is expected to run between 30/10/2015 05:00 and 30/10/2015 10:00, will be commented on.  The 30/10/2015 10:00 point represents a commercial handover position.














































Date & Start Time Power (MW) Comment Published Date & Time of Comment
30/10/2015 05:00 50
30/10/2015 05:30 100
30/10/2015 07:30 329 1) Delayed 1.5 hours. 1) Published at 08:50 30th Oct
30/10/2015 08:00 413.5
30/10/2015 09:00 329
30/10/2015 09:30 413.5 2) Delayed handover until 14:00 due to high conductivity levels       3) Delayed handover until 18:00.  Unit shutdown due to high conductivity levels.  Due to restart at 16:00 2) Published at 10:31 30th Oct     3) Published at 11:30 30th Oct

This replaces the previous post 28/10/2015 @ 14:10

----------------------------------------------------------------------------

Posted 28/10/2015 @ 14:10

Due to a further revision of the recommissioning plan, there is no requirement for Day 3 comissioning.  Therefore this notification should be seen as a cancellation.  The unit is expected to be fully available (425MW) from 29/10/2015 @ 18:30.

This replaces the previous post 27/10/2015 @ 14:25

---------------------------------------------------------------------------

Posted: 27 October 2015 @ 14:25

Please see the Day 3 post-outage recommissioning planned profile below (please scroll to the bottom of the post).  Availability is reduced from 425MW to the planned profile.

It must be noted that the planned profile will not change throughout the day of testing, but will be subject to variability.  However, significant deviations to the Day 3 recommissioning, which is expected to run between 30/10/2015 07:00 and 30/10/2015 11:30, will be commented on.  The 30/11/2015 11:30 point represents a commercial handover position.

There were no previous updates













































Date & Start Time Power (MW) Comment Published Date & Time of Comment
30/10/2015 07:00 50
30/10/2015 07:30 100
30/10/2015 08:30 329
30/10/2015 09:00 413.5
30/10/2015 10:00 303
30/10/2015 11:00 413.5

 

From: 30/Oct/2015 05:00

To: 30/Oct/2015 18:00