Severn Power REMIT

Post-Outage Recommissioning – Day 1


Category: Uncategorised

Publication according to Article 4(1) of REMIT - URGENT MARKET MESSAGE - SVRP-10

Posted 26 October 2015 @ 23:30

Day 1 commissioning has ended @ 23:24 26 October 2015, please see subsequent revision to Day 2 Post-Outage Recommissioning.

See previous updates below

-----------------------------------------------------------------------------------------------------------

Posted: 23 October 2015 @ 15:35

Please see the post-outage recommissioning planned profile below (please scroll to the bottom of the post).  Availability is reduced from 400MW to the planned profile.

It must be noted that the planned profile will not change throughout the day of testing, but will be subject to variability, with an increased likelihood of a trip event.  However, significant deviations to the Day 1 recommissioning, which is expected to run between 25/10/2015 10:00 and 26/10/2015 00:00, will be commented on.








































































































































Date & Time Start Power (MW) Comment Published Date & Time of Comment
25/10/2015 10:00 50 1) delayed by 24 hours    2) delayed by a further 6 hours    3) delayed by a further 4 hours 1) published 23rd October 2015 @ 20:20    2) published 25th October at 21:23    3) published 26th October at 19:00
25/10/2015 10:30 100
25/10/2015 11:00 20
25/10/2015 11:30 100
25/10/2015 12:00 20
25/10/2015 12:30 0
25/10/2015 13:30 50
25/10/2015 14:00 100
25/10/2015 14:30 140
25/10/2015 15:30 200
25/10/2015 16:00 250
25/10/2015 16:30 260
25/10/2015 17:00 285  2) Day 1 commissioning end point @ 27/10/2015 00:00 2) published 25th October at 21:23
25/10/2015 19:30 255
25/10/2015 20:00 285
25/10/2015 20:30 290
25/10/2015 21:00 285
25/10/2015 22:00 100
25/10/2015 22:30 285
25/10/2015 23:00 100
25/10/2015 23:30 50

 

From: 26/Oct/2015 20:00

To: 26/Oct/2015 23:25