Sutton Bridge REMIT

Planned annual Outage Extended


Category: Boiler

Publication according to Article 4 (1) of REMIT - Active Market Message - [BMU:SUTB-1]

Posted: 29th October 2015 @ 09:05

SUTB-1 availability increased to 757Mw from 09:00 29th October 2015  repair to HRSG now complete.

For further clarity: SUTB-1 is fully available form 09:00 29th October 2015

--------------------------------------------------------------------------------------------------------------------------------

Posted: 28th October 2015 @ 15:30

SUTB-1 availability decreased from 757Mw to 380 Mw from 23:30 23rd October 2015 to 19:00 29th October 2015 due to delay in repair to HRSG

For further clarity:

Between: 22:00 26 Oct-15 to 19:00 29 oct-15 - availability is 380MW

Post: 19:00 29 Oct-15 - full availability (757MW)

This replaces the post entered on the 27th  October 2015 @ 16:15

--------------------------------------------------------------------------------------------------------------

Posted: 27th October 2015 @ 16:15

SUTB-1 availability decreased from 757Mw to 380 Mw from 23:30 23rd October 2015 to 19:00 28th October 2015 due to delay in repair to HRSG

For further clarity:

Between: 22:00 26 Oct-15 to 23:30 28 oct-15 - availability is 380MW

Post: 23:30 28 Oct-15 - full availability (757MW)

This replaces the post entered on the 26th  October 2015 @ 09:15

--------------------------------------------------------------------------------------------------------------

Posted: 26th October 2015 @ 09:15

SUTB-1 availability decreased from 757Mw to 0Mw from 23:30 23rd October 2015 to 23:00 27th October 2015 due to delay in repair to HRSG and gas turbine instrumentation failure ( seen in conjunction with:  http://calonenergy.com/gas-turbine-instrumention-failure/  -  see posting 26/10/2015 09:15).

This replaces the post entered on the 23rd October 2015 @ 10:15

----------------------------------------------------------------------------------------

Posted: 23rd October 2015 @ 10:15

SUTB-1 availability decreased from 757Mw to 380Mw from 23:30 23rd October 2015 to 20:00 27th October 2015 due to delay in repair to HRSG.

This replaces the post entered on the 21st October 2015 @ 11:30
--------------------------------------------------------------------------------------------
Posted:21st October 2015 @ 11:30

SUTB-1 availability decreased from 757Mw to 380Mw from 23:30 23rd October 2015 to 23:00 26th October 2015 due to delay in repair to HRSG.

---------------------------------------------------------------------------------------

Previous Update 10th September 2015

HRSG Repair
Plant available capacity is 0 MW for the period between 23:59 11th September 2015 to 23:30 23rd October 2015.

From: 11/Sep/2015 23:59

To: 29/Oct/2015 09:00