Severn Power REMIT

Sev-10 Major 2015 Outage Move from 18Sep-24Oct to 24th September to 31st October


Category: Maintenance Outage

THIS POST HAS NOW BEEN SUPERCEDED BY POST ON 14th OCTOBER 2015

Associated changes to availability are as follows:-

 

Aug-15 (weeks 32-36): increase from 0 to 425 MW

 

18 Sep - 24 Oct: decrease from 425 MW to zero

Dates amended as follows

24th September - 31st October at zero MW

 

--

From: 24/Sep/2015 23:00

To: 31/Oct/2015 23:00