Monthly Archives: December 2014

Severn Power: unit 20


Category: Gas Turbine

Reference number / Reference number 2014/12/23[initialer]-02 Type of asset or agreement Power Plant Affected unit(s) Severn 20 Country UK Time of capacity reduction Company Macquarie Cause CHOOSE DATA Type of fuel(s) Gas Capacity influenced 410 MW Available capacity during outage … Continued

Click here to continue >>

Severn Power: unit 20 off line wash


Category: Gas Turbine

Reference number / Reference number 2014/12/23[initialer]-01 Type of asset or agreement Power Plant Affected unit(s) Severn 20 Country UK Time of capacity reduction 10.00 hrs Company Macquarie Cause Outage Type of fuel(s) Gas Capacity influenced 410 MW Available capacity during … Continued

Click here to continue >>

Severn Power: GT off line wash


Category: Uncategorised

Reference number / Reference number 2014/07/31[initialer]-xx Type of asset or agreement Power Plant Affected unit(s) Severn 20 Country UK Time of capacity reduction 23.12.2014    –   10.05 hrs Company Macquarie Cause Outage Type of fuel(s) Gas Capacity influenced 410 MW Available … Continued

Click here to continue >>

Baglan Bay: Preventative maintenance on UNIT 1 HRSG


Category: Maintenance Outage

Preventative maintenance on UNIT 1 HRSG 1.15/12/14 expected duration from 10:45 15/12/14 until  16:00 16/12/14. Availability will reduce from 480 Mw to 0 MW. Preventative maintenance on UNIT 1 HRSG 2.15/12/14 maintenance complete unit declared available from 13:15 16/12/14. Availability increased from … Continued

Click here to continue >>

Sutton Bridge: Sutton Bridge Minor Maintenance Outage


Category: Gas Turbine

SUTB-1 availability is reduced from 757MW to 370MW from 08:00 Tuesday 9th December 2014 due to maintenance outage on GT1B.  Current expected return to full availability 23:59 11th December 2014.

Click here to continue >>

Baglan Bay: Preventative maintenance on Condenser


Category: Steam Turbine

1.06/12/14 Baglan Bay is planned to be unavailable from 05:00 on Saturday 6th December 2014 to 20:00 on Saturday 6th December 2014, the associated curtailment is from 465 MW to zero MW. 2.06/12/14 Unavailability extended during test period until 02:15 … Continued

Click here to continue >>

Severn Power: Severn Unit 20 HGPI


Category: Gas Turbine

Forecast capacity reduction from 425 MW to 0 MW for the duration of this period. First fire at 09:00 on 13th June 2015 followed by a period of commissioning during which time the actual generation will vary as required by … Continued

Click here to continue >>